ST. LOUIS COUNTY GUN RANGE

Update: April 11, 2025

  • New target system pad has been poured
  • Firing station lanes are being formed and poured
  • Well drilling is underway after discovering a cave 40’ down
  • Septic system and field work have begun
  • Interior renovations are in full swing

The project includes a new water well, new septic system, roof replacement on 4 buildings, two restroom renovations, new pneumatic turning targets, and the replacement of asphalt walkways with concrete pavement.