QuikTrip #661 in Columbia, Missouri
Owner: QuikTrip Corporation
4705 S. 129th E. Avenue
Tulsa, OK 74134
Square Footage: 5,800 SF
Completion Date: August 2016
11 Week Schedule
Construction Cost: $3,900,000
Wright Construction was the General Contractor for the new Gen 3 QuikTrip in Columbia, Missouri. The project was a “super expedited” schedule requiring construction to take place 12 hours a day, 7 days a week. The project consisted of 22 pumps; extensive site work with commuter parking; shared entrance; 4 underground storage tanks; retail; and a state-of-the-art QT Kitchen.